Connect with us

Local

Eskom to implement Stage 2 Loadshedding from 12:00 until 22:00 as the power system is severely down

Published

on

Eskom to implement Stage 2 Loadshedding from 12:00 until 22:00 as the power system is severely constrained

In a statement disclosed by Eskom revealing that the power system was severely out of order after 10 generation units at seven power stations had broken down over the last 48 hours.

They said that they have lost a unit each at the Arnot, Medupi, Lethabo and Matla power stations while two units each at the Majuba, Camden and Tutuka power stations broke down.

The struggling power supplier warned that any further deterioration in the generation performance could see loadshedding being escalated at short notice, adding that the constrained power system was likely to persist for the rest of the week.

Loadshedding stage 2 for the month of September 2020

01 September 2020

12h00 to 13h30
Group 6 and 10

13h00 to 15h30
Group 7 and 11

15h00 to 17h30
Group 8 and 12

17h00 to 19h30
Group 9 and 13

19h00 to 21h30
Group 10 and 14

21h00 to 22h00
Group 11 and 15